E. Schulz et al., PLANNING, CONSTRUCTION, START-UP AND INIT IAL OPERATING RESULTS OF SCHWELGERN NO 2 BLAST-FURNACE, Stahl und Eisen, 115(11), 1995, pp. 41
The new Schwelgern No. 2 blast furnace of Thyssen Stahl AG was blown i
n on 28th October 1993. This event was preceded by a two-and-a-half-ye
ar approval procedure and a nineteen-month realization period. The pre
sent article discusses the technical concept of the new blast furnace,
the planning and realization phases up to completion, its start-up, a
nd the operating experience gained to date. Europe's largest blast fur
nace, Schwelgern No. 2, is designed for a hot metal production of 10 6
00 tpd. It has a hearth diameter of 14.9 m and a working volume of 476
9 m(3). Almost 200 contractors and 500 individual orders were involved
in its construction. A total of, inter alia, 75 000 m(3) of reinforce
d concrete, 11 000 t of reinforcing bar steel, 28 300 t of refractory
material, 44 000 t of machinery, steel and vessel components and 3 000
t of piping were required for the various parts of the plant. The con
cept of the blast furnace and its ancillary facilities is state-of-the
-art. Particular attention was paid to environmental acceptability. Th
is applies especially to the dedusting systems of the casthouses and s
tockhouse. Solutions that had been tried and proven in-house as well a
s successfully tested internationally were used for the refractory lin
ing and cooling systems. Eighty percent of the rated capacity were att
ained as early as November 1993. Following a production of 3.2 million
tonnes of hot metal in 1994, it was possible in July 1995 to achieve
the highest hot metal output in a month so far at 333 000 t.