J. Hoffer, MODELING THE PARTIAL PLANNED OUTAGES IN PRODUCTION COSTING SIMULATION, INTERNATIONAL JOURNAL OF ELECTRICAL POWER AND ENERGY SYSTEMS, 17(6), 1995, pp. 377-380
This paper presents two ways of modelling such scheduled maintenance w
hose length is less than that of the simulation period (called partial
planned or scheduled outages in the paper). The present author sugges
ts using modified forced outage rate instead of derated capacity in th
is case. The effect of the different representations is shown on a ver
y simple numerical example by comparing the loss-of-load probability,
the energy not served and the expected energy generations of the units
. The paper concludes that the modification of the forced outage param
eter of units is more appropriate than derating the capacity.