D. Golenkoginzburg et A. Gonik, ONLINE CONTROL MODEL FOR COST-SIMULATION NETWORK PROJECTS, The Journal of the Operational Research Society, 47(2), 1996, pp. 266-283
Citations number
29
Categorie Soggetti
Management,"Operatione Research & Management Science","Operatione Research & Management Science
This paper presents a newly developed hierarchical control model for s
everal PERT type projects being realized simultaneously. The model has
two objectives: to minimize the number of control points for an on-li
ne control at the project level, and to maximize the probability that
the slowest project can meet its due date on time (company level). On-
line control is carried out separately for each project in order to mi
nimize the number of control points subject to a chance constraint, wh
ich seeks to prevent deviation from the planned trajectory. If at the
control point it is anticipated that the project will not be on target
subject to the chance constraint, then an emergency is called. Under
emergency conditions the company level is faced with the stochastic pr
oblem of budget reassigning among the projects enabling the faster pro
jects to help the slower ones. A numerical example is presented.