This paper deals with a production scheduling problem in the two-stage
hybrid how shop, when there is one machine at the first stage and the
second stage consists of different kinds of machine. First, the total
flowtime or makespan and the maximum work-in-process are formulated a
s criteria for manufacturing performance. Further, the effect of the l
ot sizing and sequencing on these criteria is examined through a serie
s of numerical experiments.