Examines the planning and scheduling systems in an integrative framewo
rk for a dual resource constrained (DRC) job shop. Models a bottleneck
shop environment which represents a common situation in practice. Res
earch on workload smoothing mechanisms which integrate the planning an
d scheduling systems is sparse. Simulates 13 smoothing rules (utilizin
g aggregate workload and bottleneck information), three despatching ru
les and two order review/release rules. The results of this study indi
cate that workload smoothing by the planning system has a significant
effect on the performance of the DRC job shop. Pulling work ahead in v
alley periods improved the tardy measures of performance, while pushin
g jobs back in peak periods usually deteriorated shop performance. Sug
gests that combining a planning system effectively with order review/r
elease can improve mean tardiness, percentage tardy and mean flowtime
measures of performance.