A. Sprecher et al., SEMIACTIVE, ACTIVE, AND NON-DELAY SCHEDULES FOR THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM, European journal of operational research, 80(1), 1995, pp. 94-102
Citations number
30
Categorie Soggetti
Management,"Operatione Research & Management Science
We consider the resource-constrained project scheduling problem (RCPSP
). The focus of the paper is on a formal definition of semi-active, ac
tive, and non-delay schedules. Traditionally these schedules establish
basic concepts within the job shop scheduling literature. There they
are usually defined in a rather informal way which does not create any
substantial problems. Using these concepts in the more general RCPSP
without giving a formal definition may cause serious problems. After p
roviding a formal definition of semi-active, active, and non-delay sch
edules for the RCPSP we outline some of these problems occurring withi
n the disjunctive are concept.