REGRESSION-BASED DUE-DATE ASSIGNMENT RULES FOR IMPROVED ASSEMBLY SHOPPERFORMANCE

Citation
Ch. Smith et al., REGRESSION-BASED DUE-DATE ASSIGNMENT RULES FOR IMPROVED ASSEMBLY SHOPPERFORMANCE, International Journal of Production Research, 33(9), 1995, pp. 2375-2385
Citations number
NO
Categorie Soggetti
Engineering,"Operatione Research & Management Science
ISSN journal
00207543
Volume
33
Issue
9
Year of publication
1995
Pages
2375 - 2385
Database
ISI
SICI code
0020-7543(1995)33:9<2375:RDARFI>2.0.ZU;2-B
Abstract
Many simulation studies have evaluated sequencing rules and due date a ssignment methods for scheduling job shops. More recently researchers have studied multistage, or assembly, shops. Typically, due dates have been set by using a fixed multiple of the critical path length. This paper evaluates the effects on shop performance due to using a regress ion-based approach for setting due dates. The findings show that marke d improvement in the performance of dispatching rules can occur when t he proposed due date setting procedure is used.