The fuel handling plant at Torness power station has been functioning
since 1989 under operational constraints due to perceived shortfalls i
n the as-built equipment. This has limited the achievable station load
factor. This Paper describes the nature of these shortfalls, and the
work to rectify them which is currently nearing completion.