Pe. Yundt et al., HEURISTIC AND SIMULATION TECHNIQUES FOR THE SCHEDULING OF HAZARDOUS-WASTE PROCESSING IN AN INTEGRATED TREATMENT FACILITY, Canadian journal of civil engineering, 21(5), 1994, pp. 752-761
The basic strategies for optimizing processing schedules of hazardous
waste in an integrated hazardous waste treatment facility are analyzed
. Five schedule optimization heuristics were evaluated on six simulati
on models of hypothetical integrated hazardous waste treatment facilit
ies. The six models represented combinations of one of three unit proc
ess configurations and one of two facility operating policies. The heu
ristics were evaluated with respect to their ability to minimize the a
verage completion time (makespan) of a specified set of jobs. The same
five heuristics were applied to a model representing the physical and
chemical treatment plant of the Alberta Special Waste Management Corp
oration. Operation under two operating policies for this case study wa
s evaluated, and the results were compared with the hypothetical model
results. Some heuristics were found to be capable of reducing makespa
ns by 13-14% relative to the first in, first out heuristic.