H. Matsuura et H. Tsubone, SETTING PLANNED LEADTIMES IN CAPACITY REQUIREMENTS PLANNING, The Journal of the Operational Research Society, 44(8), 1993, pp. 809-816
Citations number
9
Categorie Soggetti
Management,"Operatione Research & Management Science","Operatione Research & Management Science
This paper deals with the problem of determining planned leadtimes in
a periodic loading system, such as 'Material Requirements Planning.' A
method for determining planned leadtime for an individual job, based
upon the operation time for the job, is presented from the standpoint
that the planned leadtime should be determined under a management poli
cy, taking a trade off between work-in-process quantities and capacity
requirements variations into consideration. The proposed method, whic
h is derived with Lagrange's method of indeterminate coefficients, can
minimize capacity requirements variations under a given average loadi
ng time, under general operation time distributions.