Ff. Boctor, HEURISTICS FOR SCHEDULING PROJECTS WITH RESOURCE RESTRICTIONS AND SEVERAL RESOURCE-DURATION MODES, International Journal of Production Research, 31(11), 1993, pp. 2547-2558
Citations number
NO
Categorie Soggetti
Engineering,"Operatione Research & Management Science
The problem addressed in this paper is the non-preemptive resource-con
strained project scheduling problem in which the duration of each acti
vity depends on the amount of resources allocated to its execution, an
d the objective is to minimize the overall project duration. It is als
o assumed that resources are limited but renewable from period to peri
od. Twenty-one heuristic scheduling rules are compared on 240 test pro
blems divided into two main groups containing 50 and 100 activities, r
espectively. Each group contains one-resource, two-resource and four-r
esource problems. The results of the comparative study allow us to ide
ntify the most efficient heuristics and suggest a combination of five-
heuristics which have a high probability (229 over 240) of giving the
best (among the 21 solutions obtained) solution.