G. Ballard et G. Howell, SHIELDING PRODUCTION - ESSENTIAL STEP IN PRODUCTION CONTROL, Journal of construction engineering and management, 124(1), 1998, pp. 11-17
Citations number
15
Categorie Soggetti
Construcion & Building Technology","Engineering, Civil","Engineering, Industrial
Effective production control systems are structured around the assignm
ent as the unit of analysis. The quality of work assignments in produc
tion units such as construction crews and engineering squads is the ke
y to production control and for determining production unit productivi
ty. Research has revealed that the quality of assignments can be subst
antially improved by forming and selecting them to meet soundness, seq
uence, and size criteria. Quality assignments shield production units
from work flow uncertainty, enabling those units to improve their own
productivity, and also improve the productivity of the production unit
s downstream. The associated reduction in task duration can shorten pr
ojects. Further reduction of project duration comes from shortening th
e buffers previously needed to accommodate flow uncertainty.