A scheduling method is elucidated for the re-entrant manufacturing systems,
where the process route of a job passes production facilities one or more
times. The objectives of the scheduling problem are maximization of the pro
duction rate as a primary one and minimization of the throughput time as a
secondary one. The method makes the cyclic schedule, where an adequate numb
er of jobs are treated as a lot and the lot is cyclically released into the
system. The lot size is determined to maximize the production rate, and a
sequencing method of the lots is developed to minimize the throughput time.
(C) 1999 Published by Elsevier Science B.V. All rights reserved.