Field stringing test near a live conductor at the Hokkaido-Honshu HVdc link line

Citation
T. Suda et al., Field stringing test near a live conductor at the Hokkaido-Honshu HVdc link line, IEEE POW D, 14(3), 1999, pp. 1062-1068
Citations number
8
Categorie Soggetti
Eletrical & Eletronics Engineeing
Journal title
IEEE TRANSACTIONS ON POWER DELIVERY
ISSN journal
08858977 → ACNP
Volume
14
Issue
3
Year of publication
1999
Pages
1062 - 1068
Database
ISI
SICI code
0885-8977(199907)14:3<1062:FSTNAL>2.0.ZU;2-0
Abstract
A +/-500kV HVdc transmission line is currently being constructed jointly by some electric power companies in Japan. Following construction of this ove rhead transmission Line, the ability to work near a live line in a safe man ner is one of the most important factors for system reliability. We conduct ed a survey of work near a live line using the +/-250kV Hokkaido-Honshu HVd c Link Line in July 1990 before this overhead transmission line was upgrade d. As a result, we clarified various problems in the work conducted near a Live line and suggested some countermeasures such as the grounding of strin ging conductors at more than one point.