Formal stochastic simulation study has been recognized as a remedy for the
shortcomings inherent to classic critical path method (CPM) project evaluat
ion and review technique (PERT) analysis. An accurate and efficient method
of identifying critical activities is essential for conducting PERT simulat
ion. This paper discusses the derivation of a PERT simulation model, which
incorporates the discrete event modeling approach and a simplified critical
activity identification method. This has been done in an attempt to overco
me the limitations and enhance the computing efficiency of classic CPM/PERT
analysis. A case study was conducted to validate the developed model and c
ompare it to classic CPM/PERT analysis. The developed model showed marked e
nhancement in analyzing the risk of project schedule overrun and determinat
ion of activity criticality. In addition, the beta distribution and its sub
jective fitting methods are discussed to complement the PERT simulation mod
el. This new solution to CPM network analysis can provide project managemen
t with a convenient tool to assess alternative scenarios based on computer
simulation and risk analysis.