An approach using linear programming based on grey constrained interva
l is applied to solve the short-term hydro scheduling problem. A chara
cteristic feature of this approach is that the errors in the forecast
hourly loads and natural inflows can be taken into account by using gr
ey number notation, making the approach superior to the conventional l
inear programming method in which the hourly loads and natural inflows
are assumed to be exactly known and there are no errors in the foreca
st loads and natural inflows. To reach an optimal scheduling under the
uncertain environment, a grey linear programming model in which the h
ourly loads, the hourly natural inflows are all expressed in grey numb
er notation, is developed. The developed grey linear programming appro
ach is applied to schedule the generation in the Taiwan power system.
It is found that the proposed approach is very effective in obtaining
proper hydro generation schedules in uncertain conditions. (C) 1997 El
sevier Science S.A.