Ss. Erenguc et al., The resource constrained project scheduling problem with multiple crashable modes: An exact solution method, NAV RES LOG, 48(2), 2001, pp. 107-127
We introduce a formulation and an exact solution method for a nonpreemptive
resource constrained project scheduling problem in which the duration/cost
of an activity is determined by the mode selection and the duration reduct
ion (crashing) within the mode. This problem is a natural combination of th
e time/cost tradeoff problem and the resource constrained project schedulin
g problem. It involves the determination, for each activity, of its resourc
e requirements, the extent of crashing, and its start time so that the tota
l project cost is minimized. We present a branch and bound procedure and re
port computational results with a set of 160 problems. Computational result
s demonstrate the effectiveness of our procedure. (C) 2001 John Wiley & Son
s, Inc.